Pool Renovations
A 2004 Bond Election authorized $1.7 M for
Rosemeade Pool renovations and $300,000 for Thomas Center Pool
renovations.
Rosemeade
Pool Improvements
Upgrade aging
pump, drain & circulation systems
Demolish existing wading pool
Eliminate non-compliant 5m platform tower
Add new zero-depth entry pool with various pool features including
water slide
Add shade structures, extend fence and other items - chairs, pool
decking and landscaping
Begin Construction in mid September 2006
Design completion in mid-June 2006
Construction complete and pools open on Memorial Day, May 28, 2007
Thomas Pool Improvements
Upgrade aging pump machinery
Address non-compliant wading pool
Add shade structures, extend fence and landscaping
Same schedule as Rosemeade Pool
Click on photos for
larger view.

SKILES PROPERTY
2335 Sandy Lake Road
The design of soccer fields and related amenities is near completion. Staff has met with
the local sports associations to include their input into the final design.
Construction is near completion and use is anticipated in the spring of 2007. Please call the
Parks & Recreation administrative offices at 972-466-3080 for more
information.
MAINTENANCE FACILITY
2205 Sandy Lake Road
Parks
Maintenance Staff will be moving from the
location behind W.J. Thomas Pool to the Rural America site northeast
of McInnish Sports Complex. The facility is currently under design and
expected to be complete in winter 2006. Please call the Parks & Recreation
administrative offices at 972-466-3080 for more
information.